St James Primary School, Elstead, Surrey
Plant Room Refurbishment
THE PROJECT:
Name: St James Primary School
Nature: Plantroom Refurbishment
Location: Thursley Road, Elstead, Surrey, GU8 6DH
![](https://i0.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5959.jpg?resize=1024%2C1021&ssl=1)
The Mechanical Services installation includes for the supply, delivery, installation, connection, testing and commissioning of all equipment within the main plant room.
The scope of works consisted of the following:
- Strip-out and disposal of plantroom equipment
- Removal of Biomass boiler and equipment.
- Modifications to the existing gas service
- Installation of new gas-fired condensing boilers
- Installation of new flue system
- Installation of new plantroom equipment
- Design & installation of new controls
- Pre commissioning and cleansing.
- Testing and commissioning
- Builders work in connection with Mechanical works
- Provision of record documentation
Image Gallery from this project
![](https://i1.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5960-1024x1020.jpg?ssl=1)
![](https://i2.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5961-1024x1020.jpg?ssl=1)
![](https://i0.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5962-1024x1006.jpg?ssl=1)
![](https://i2.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5963-1024x1014.jpg?ssl=1)
![](https://i0.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5964-1024x1013.jpg?ssl=1)
Image Gallery of the previous installation from this project
![](https://i0.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5965-1024x1007.jpg?ssl=1)
![](https://i0.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5968-1024x1012.jpg?ssl=1)
![](https://i2.wp.com/comgas.uk/wp-content/uploads/2023/09/IMG_5967-1024x1017.jpg?ssl=1)
Contact us
Please contact us to arrange a site survey for your next project.
Follow on Social